Halliburton, the cementing contractor, advised BP to install numerous devices to make sure the pipe was centered in the well before pumping cement, according to Halliburton do ents, provided to congressional investigators and seen by the Journal. Otherwise, the cement might develop small channels that gas could squeeze through.
In an April 18 report to BP, Halliburton warned that if BP didn't use more centering devices, the well would likely have "a SEVERE gas flow problem." Still, BP decided to install fewer of the devices than Halliburton recommended—six instead of 21.