* September 29, 2008 an 8 inch high pressure gas line at the Y-Pad location “separated” sending 3 pieces of pipe to the tundra. One segment of the pipe landed 900 feet from the pipeline. Roughly 30 minutes later a second and unrelated incident occurred on the S Pad where there was a gas release.
* January 15, 2009 a isc cleaning pig became lodged and lost in a 34 inch Oil Transit Line during de-oiling allowing gas to pass around the pig and travel through Skid 50, to Pump Station 1 causing a significant venting of gas to the atmosphere and the complete shutdown of the Trans Alaska Pipeline for a period of time.
* October 10, 2009 at the Central Compressor Plant low pressure flare staging valves were stuck closed causing gas to travel to the backup low pressure flare valves, which activated causing the gas to vent to the atmosphere which could have caused an explosion.
* November 29, 2009 an 18 inch three-phase common line near the Lisburne Production Center carrying a mixture of crude oil, produced water and natural gas ruptured spraying its contents over an estimated 8,400 square feet area.